Re-routing Hall Electricity Supply

Mon 28-Sep-2015 by Martin Bond

5-dscf1821
Week beginning 28th September work was started and completed on the re-routing of the electrical supply to the Parish Hall.

The supply previously entered the Hall under the old barn door on the east side of the building and was routed under the floor to the meter and consumer units on in the cupboard adjacent to the Hall door on the west side of the building.

To complete the work on the floor and installation of the underfloor heating the cable had to be moved. The new location for the meter is in the storeroom. As all the Hall electrical circuits currently are fed from the consumer unit in the cupboard in the Hall, and as the work to installing new circuits will not commence until February 2016, a temporary power supply has been laid from the new location of the meter to the existing consumer units.

4-dscf1820
To relocate the cable required a trench to be dug in ‘Campie’s yard’ and we are extremely grateful to Campie and Barnabas for allowing this to happen in support of the project. The trench was dug on Monday. To gain access to the storeroom from the trench required an access hole to be dug in the floor of the storeroom and under the storeroom external wall. This was completed on Tuesday by Ron Moore and Steve Baber.

On Thursday Dart Electrics were at the Hall to undertake the necessary electrical work in installing the equipment and cable to connect the new power source to the existing consumer units. Western Power were at the Hall and moved the cable to the new location and fitted the meter. By the end of the day on Thursday this part of the work was completed and the electric services and equipment in the Hall were tested and functioned.

Friday saw the backfilling of the trench.

Photographs of the work

More photos on our Picasa slideshow

View Slideshow
01-dscf1745 Trench for cable by east wall
06-dscf1750 Safety barrier guarding the trench
3-dscf1819 Cable under wall into store room
4-dscf1820 Cable laid in trench

5-dscf1821 New supply and fuse box
63-dscf1807 Richard Boyles connecting temporary supply
68-dscf1812 Western power on site as agreed (but not EDF energy)
7-dscf1823 Temporary power supply cable

9-dscf1825 Power supply to old fuse box
  1. History Blog

    • VE 80th Anniversary Exhibition Fri 09-May-2025
      The VE80 Exhibition in the Parish Hall was put together ...
    • Heritage Project Group Photo Call Fri 20-Feb-2015
      Early (well 9:30 which isn’t that early really) on a ...
  2. More blog posts…

 

  1. Community Diary

    • VE 80th Anniversary Exhibition Fri 09-May-2025
      The VE80 Exhibition in the Parish Hall was put together ...
    • Crocus and Cream Teas 2025 Sun 23-Mar-2025
      The annual crocus and cream tea event for Sunday 23rd ...
  2. More diary entries…

 

  1. Parish Hall Newsletters

    • VE 80th Anniversary Exhibition Fri 09-May-2025
      The VE80 Exhibition in the Parish Hall was put together ...
    • Crocus and Cream Teas 2025 Sun 23-Mar-2025
      The annual crocus and cream tea event for Sunday 23rd ...
  2. More newsletters..

 

  1. Heritage Diary

    • Worlington Revel Mon 27-Jul-2020
      Research into Worlington Revel revealed the following information through newspaper ...
    • Online Timeline Sun 26-Jul-2020
      One activity undertaken as part of the Heritage Projects (2015-2017) ...
  2. More heritage entries…

Copyright © 2025 · East Worlington Parish Theme on Genesis Framework · WordPress · Log in